Level 5 · Practical exam

Commission the air-handler program

Run your installed virtual controller against occupied and unoccupied operation, loss of permissives, timing boundaries and recovery. Finish the independent commissioning sequence.

Practical evidence

Your verified practical records are attached below. The signed report and an independent knowledge pass are both required. The simulator verifies the practical checks. Your written conclusion is retained for review.

Practical outstanding.

Independent transfer assessment

Pass at 80%. Every safety item must also pass.

1. An on-delay timer enables an output after three uninterrupted 5-second intervals. The enable drops in the second interval. What should the next start use?
2. Before accepting a deployed change, what must you verify? · Required for safety
3. Which test exposes an unsafe restart that a normal startup may miss?
4. Temperature error stays high with the valve saturated. Branch flow is zero. What is the first defensible action?
5. A training proportional-only heating loop uses output = 8% per °F × (target − measured) with zero bias. Target is 70°F and measured is 66°F. Find the unclamped output.