What you’ll learn
- Classify physical and software points from the controller’s perspective.
- Select independent evidence of a fan or valve response.
Before you start · 2 related lessons
0 of 2 prerequisites demonstrated. You can open this lesson at any time.Read the point from the controller’s side
An analog input (AI) measures a range such as temperature. A binary or digital input (BI or DI) senses two states such as a contact. An analog output (AO) can request position or speed. A binary or digital output (BO or DO) can request start. A The active target after applicable schedules, resets, limits and priority selection. , calculated flow or occupancy mode can exist entirely in software. A network object with an input-like name can obtain its value from a different controller. Use the I/O schedule and object binding to find its origin.
Trace the whole proof chain
For a fan, distinguish the effective start The effective instruction issued to a device. Compare it with actual travel, rotation or flow. , the drive’s run indication and delivered air. An auxiliary contact reports contactor state. A current switch responds to current. A duct differential switch changes at its configured pressure threshold. A traverse measures flow at a defined duct section. Each observation covers a different part of the path. A display can label an echoed command as A returned observation such as position or speed. Locate the pickup to see which part of the mechanism it represents. , so check what drives the value.
- SF-CMD · request
- Drive run contact · status
- Shaft speed · movement
- Duct flow · delivered air
Normal operation
Example training conditions
- The start output is On, the run input is On, the speed output requests 60% and the independent duct traverse reads 2,400 cfm.
- Label the binary points as start and proof, the modulating point as the speed request and the traverse as a physical measurement.
Worked service example
The training AHU graphic says the supply fan is on. Several outlets have little air.
Recorded field evidence · training example
- SF-CMD = On. Drive status contact = Closed.
- Fan speed feedback = 70%. Measured duct airflow = 950 cfm.
- Prior balanced airflow under matching conditions = 3,600 cfm.
The request and drive indication agree, but the duct result is low. Verify local rotation, dampers, filters and the measurement location. Relabeling the fan-status input cannot establish where the missing air went.
Field procedure
- Write down the tag, asset, unit, source and time.
- Find the effective output and inspect local feedback.
- Choose a measurement downstream of the suspected failure.
Hands-on exercise
Command two actuator positions. Record the measured terminal voltage and shaft witness at each position, then restore automatic control.
Two-endpoint actuator checkout
The approved submittal maps 2–10 V to 0–100% travel. At each endpoint compare the BAS request with the actuator terminal voltage and shaft witness mark. Return the point to automatic control.
Recorded positions · NoneRecord the low and high terminal readings and return the output to automatic control.
Unit 1 service call
The BAS says the supply fan is on. Can you prove the building is receiving air?
Find an independent witness that air reaches the occupied area. Bring back the source, reading and time of your strongest observation.
Open case simulatorStandalone simulator · free practice
Compare fan command, speed and flow
Capture the available local airflow measurement. Compare it with the command and indicated speed in the equipment and points views.
Open simulator →Knowledge check
Pass at 80%.
Field takeaways
- Classify input and output relative to the controller.
- Choose proof downstream of the failure you are testing.