What you’ll learn

  • Locate a control decision in the building architecture.
  • Separate an unavailable workstation reading from a stopped piece of equipment.
Before you start · 2 related lessons0 of 2 prerequisites demonstrated. You can open this lesson at any time.

Follow one occupied start

At occupied start a schedule can send an enable to the air handler. A field controller applies its start sequence, reads permissives and issues an output. A drive accepts that request and accelerates a motor. A pressure switch or airflow instrument gives the controller another observation. The workstation draws a graphic from the reported points. Each part answers a different question about the same start.

Find the owner of each decision

Building automation system (BAS) and building management system (BMS) are overlapping project terms. HVAC controls include the sensors, switches, software and final devices that regulate mechanical equipment. Direct digital control () describes a controller sampling inputs, executing logic and updating outputs. Supervisory controllers may coordinate multiple units, schedules and histories. A sequence can also reside locally. Read the project architecture and points list to determine who owns each function and what happens when communication stops.

Use time and place

A graphic can retain the last good value after a field controller goes offline. Compare its timestamp and quality with a second local observation. If other controllers on the same supervisor continue updating, work toward the affected branch. If the field controller keeps controlling locally, ask which remote setpoints or schedule values it normally needs and how their loss is handled.

An occupied start and its reporting path
  1. Supervisor sends enable
  2. Field DDC evaluates inputs
  3. Output starts drive
  4. Fan develops airflow
  5. Proof returns to DDC
  6. Workstation displays status

Normal operation

Example training conditions

  • At 08:10 an occupied air handler shows a 40 Hz drive output locally. The workstation reports 40 Hz with an 08:10 update; a field traverse finds 3,000 cfm.
  • The matching displays establish current reporting at that instant. The traverse separately establishes air delivery at the measurement section.

Worked service example

The front desk sees the fourth-floor fan frozen at its morning speed.

Recorded field evidence · training example

  • Workstation last update 08:10. Inspection at 08:42.
  • Drive display 43 Hz. Local airflow 3,200 cfm.
  • Adjacent floor values updated at 08:42.

Air is moving at the observation time. The old value narrows the next check to reporting from the affected controller. Verify its local clock, communications status and upstream path before disturbing the running unit.

Field procedure

  1. Record the affected unit, operating mode and time of complaint.
  2. Locate the sequence owner and identify which values cross the network.
  3. Compare local status with the supervisor’s point quality, timestamp and neighboring controllers.

Hands-on exercise

Locate the supervisor and a field controller in the network diagram. Predict which readings the supervisor would lose if that controller stopped communicating.

Follow a local fan through a reporting outage

The AHU controller runs its own fan loop. Compare two synchronized inspections at 08:10 and 08:42. The last reported value stays on the graphic until the next successful update.

BACnet/IP
MS/TP trunk
Supervisor · AHU fan 36 Hz, last update 08:10. The neighboring fan is current.

Compare the supervisor's original and current report, the local AHU and the unaffected neighbor. Record the age of the AHU's reported speed.

Unit 1 service call

The BAS says the supply fan is on. Can you prove the building is receiving air?

Find an independent witness that air reaches the occupied area. Bring back the source, reading and time of your strongest observation.

Open case simulator

Knowledge check

Pass at 80%.

1. The supervisor shows a 09:42 fan sample when the local controller clock reads 09:49. Assuming synchronized clocks, how many minutes old is that sample?
2. An operator needs to know whether a failed supervisor will interrupt a freeze-protection function. Which record resolves ownership?
3. Only one AHU freezes on the workstation. Its controller shows changing values and the drive is running. Which check best narrows the fault?
4. The supervisor can see a field controller, but an attached thermostat reads 0°F locally and at the workstation. Where is the first useful comparison?
5. An AHU uses a local pressure loop and receives its occupied mode from the supervisor. What determines operation during a network outage?

Field takeaways

  • Identify where each sequence runs and which inputs arrive over the network.
  • Check the time and source of every observation.

References and further reading