What you’ll learn
- Separate a start request, run permission and physical delivery.
- Choose a test that distinguishes two plausible failures.
Before you start · 2 related lessons
0 of 2 prerequisites demonstrated. You can open this lesson at any time.Start at the first disagreement
Write the expected chain for this operating mode. At a fan, a start request can be present while the controller output, relay contact or drive A condition the sequence requires before an action, such as a ready input before a fan start. is missing. A proven spinning motor can still deliver little air through a failed belt or blocked path. Check an independent observation downstream of the last confirmed stage.
Preserve the event history
For an intermittent shutdown, find the first lost permissive or alarm in time. A fan- An observation satisfying a defined criterion. A current switch proves current above its threshold. A duct switch proves pressure differential at its taps. alarm after a safety trip can be a consequence of the stop. Trigger times, sensor sampling rates, separate device clocks and failure-to-prove delays can change apparent event order. Retain local indications before resetting the simulated unit.
- Occupancy and effective request
- Control power and run permission
- Drive and motor feedback
- Delivered airflow and duct pressure
Normal operation
Example training conditions
- A normal occupied fan command reaches the relay at about 24 VAC; the drive receives run permission, shaft speed rises and measured duct airflow reaches 2,200 cfm.
- Use this ordered chain as the expected condition before comparing a failed run.
Worked service example
A meeting suite has no air after morning start.
Recorded field evidence · training example
- Start request on. Drive run status off.
- Independent air reading 0 cfm. No overload event in this interval.
- The upstream AHU serving the neighboring suite runs normally.
This localizes the symptom to one equipment path. Test control power and drive permission before deciding whether the fault is wiring, a drive or a mechanical load.
Field procedure
- Identify the first abnormal transition and its time.
- Predict the two different outcomes of the next independent test.
- Keep a record of the actual reading, repair and sustained restored operation.
Hands-on exercise
Compare the signal across the control supply with the voltage at the load before choosing the next test.
Trace the fan relay circuit
Record the live control source and relay coil voltages. Open and lock the simulated disconnect, prove the secondary dead, lift the test link and record the isolated coil resistance. Compare the three readings to locate the failed component.
Scroll the diagram sideways to reach all six terminals, or use the lead selectors.
F1 supplies the controller and the series start path. K1’s normally open contact grants the drive run permission. The enclosed primary and motor feeder are outside the test board.
Digital multimeter
Control disconnect closed · Unlocked · Secondary unverified · Coil link connected.
0 of 3 diagnostic measurements recorded.
Unit 11 service call
The equipment is running normally now. What happened overnight?
Separate the initiating event from its consequences and give the next shift a retest plan. Bring back the source, reading and time of your strongest observation.
Open case simulatorStandalone simulator · free practice
AHU-11 electrical service call
Use the work-order meter, diagnose the fan circuit, make the authorized simulated repair and collect sustained operating proof.
Open simulator →Knowledge check
Pass at 80%.
Field takeaways
- Start with the sequence and a discriminating observation.
- Keep initiating and consequential alarms distinct.