What you’ll learn

  • Reconcile equipment, panel and network identifiers.
  • Flag a design-to-installation discrepancy with its revision.
Before you start · 2 related lessons0 of 2 prerequisites demonstrated. You can open this lesson at any time.

Read the documents in layers

Use the mechanical plan to find the equipment and service area. Follow the piping or duct schematic to establish what the device measures. The controls submittal adds the sensor range, signal type, terminal and sequence. The points list maps that physical item to a controller object. The network riser locates the controller on its segment and router. Compare the revision dates and record any disagreement.

Keep identity when friendly names repeat

A floor can have many objects called Supply Temp. Record the asset, controller device instance, object type and instance, units and sensor location. The same object number can occur on two different devices. If the drawing and installation differ, preserve the actual readings and mark up the discrepancy for the responsible engineer before editing the graphic.

Trace the numbered device
  1. Mechanical schedule and location
  2. Controls drawing and terminal
  3. Points list and device object
  4. Riser and supervisor binding

Normal operation

Example training conditions

  • An approved points list assigns the conference room sensor to one controller input. Its wire label, input channel and workstation object all identify that same zone; the local and graphic readings update together.
  • Repeat the trace for each similarly named point so a good reading from the wrong room cannot pass checkout.

Worked service example

An AHU graphic shows the other building wing's supply temperature.

Recorded field evidence · training example

  • North controller Device 11001, AI-17 at 54.8°F.
  • South controller Device 11002, AI-17 at 61.7°F.
  • North graphic binding points to 11002 / AI-17.

The object number matches in both controllers. The device address maps the North graphic to the wrong source.

Field procedure

  1. Collect current drawing and submittal revisions.
  2. Cross-reference the tag, field label, terminal and object address.
  3. Confirm a change at the correct source reaches only the intended graphic.

Hands-on exercise

Trace the router and both terminal controllers on the riser. Compare their device instances with their local MS/TP addresses.

Reconcile a riser with the installed point binding

Revision C of the approved riser serves the north and south terminals through network 210. Compare it with the as-found point sources. AI-17 is a valid temperature input on each terminal.

BACnet/IP
MS/TP trunk
Supervisor · North discharge is assigned to the north controller's AI-17.

Inspect the approved router record and the three as-found sources. Report the north terminal’s MAC and the discrepancy to correct.

Unit 2 service call

The pressure on the graphic disagrees with the field transmitter.

Locate the first disagreement between the field signal, controller conversion and displayed value. Bring back the source, reading and time of your strongest observation.

Open case simulator

Knowledge check

Pass at 80%.

1. A controller input is labeled AI-4 in the panel, and two BAS values have nearly identical zone names. What trace justifies selecting one binding?
2. A drawing revision changed the sensor location after installation. Which field record makes a later diagnosis reproducible?
3. Which pair uniquely locates this process object on the simulated BACnet internetwork?
4. The installed actuator has a 2–10 V input but a draft controls diagram shows 0–10 V. Which action is defensible before checkout?
5. The points list and latest mechanical schedule specify different sensor locations. What belongs in the discrepancy record?

Field takeaways

  • Use physical and network identities together.
  • Version the documents you used to make the decision.