What you’ll learn
- Write an acceptance criterion with an explicit timer and reset condition.
- Separate a failed sequence from a poorly tuned loop.
Before you start · 2 related lessons
0 of 2 prerequisites demonstrated. You can open this lesson at any time.Test both edges of the condition
Turn the approved sequence into an initial state, stimulus, expected outputs, allowed time and recovery condition. Exercise normal start, shutdown and the authorized simulated failure. A delay specified as continuously missing An observation satisfying a defined criterion. A current switch proves current above its threshold. A duct switch proves pressure differential at its taps. should reset if proof returns before expiry. Record the condition, annunciation, acknowledgement and return-to-normal as separate events.
Tune after establishing authority
Trend the The active target after applicable schedules, resets, limits and priority selection. , sensor, effective output, actuator position and measured response on a common clock. A saturated valve or stuck shaft removes the loop's ability to control the process. Resolve those limits before changing gains. Test one tuning change at a time under a comparable disturbance, then document overshoot, settling time, remaining error and rollback.
- Initial mode and conditions
- Timed stimulus
- Expected transition
- Recorded response
- Return to automatic
Normal operation
Example training conditions
- A training fan sequence allows a ten-second proof window. With a normal start, proof arrives after six seconds. The start remains enabled and the fault alarm stays clear.
- Repeat with a controlled interruption, record the alarm timing and verify automatic recovery according to the approved test script.
Worked service example
The acceptance test requires an alarm after 30 continuous seconds of missing fan proof.
Recorded field evidence · training example
- Proof lost at t=0 and restored at t=20 s.
- Proof lost again at t=40 s and remains off through t=75 s.
- Report timestamps and controller timestamps share the test clock.
The second interval reaches 30 seconds at t=70. An alarm at t=50 suggests the implementation accumulated separate intervals.
Field procedure
- Document the approved revision, scope, acceptance limits and recording interval.
- Run a short interrupted failure and a long sustained failure.
- Restore all simulated conditions, collect final trends and flag any untested modes.
Hands-on exercise
Apply a repeatable disturbance, then compare overshoot and settling with one gain changed.
Duct static PID bench
Record a P-only offset by advancing 60 seconds at the starting load. Keep that target and load, add integral action, then hold pressure within 0.06 in. w.c. for ten samples with the output inside its limits. Try an integral gain of 1 and allow several minutes for recovery.
P 0.00 · I 0.00 · D 0.00 percentage points of output
Unit 10 service call
A checkout point moves in the wrong direction under load.
Leave a reproducible point-to-point, functional and restoration record. Bring back the source, reading and time of your strongest observation.
Open case simulatorStandalone simulator · free practice
DDC block laboratory
Exercise a timer with a brief false input before its full delay, then hold the input continuously. Record when its output changes.
Open simulator →Knowledge check
Pass at 80%. Every safety item must also pass.
Field takeaways
- Acceptance includes both activation and recovery.
- Capture as-found and as-left operation with timestamps.