What you’ll learn

  • Distinguish a VAV box, recirculating fan coil and dedicated outdoor air system.
  • Check sensible capacity and moisture removal on the equipment assigned to each load.
Before you start · 3 related lessons0 of 3 prerequisites demonstrated. You can open this lesson at any time.

Find where the cold air originates

A pressure-independent box compares a flow measurement with a changing flow target and modulates its inlet damper. A downstream reheat coil may temper low cooling airflow during heating. A fan coil instead moves local air over a water coil. On a two-pipe changeover system the available water temperature limits which mode it can deliver. Confirm the water source, fan and control valve before judging its capacity.

Track ventilation separately

A dedicated outdoor air system (DOAS) conditions outdoor air for one or more zones. In a design with sensible-only terminals, the central unit must dry the ventilation stream sufficiently to handle the assigned moisture load. A cool thermostat can coexist with elevated zone dew point. Check the DOAS discharge dew point, outdoor-air flow to the affected zone and any air leaks before changing its terminal temperature.

Observe an air-source heat pump through defrost

During a heating call the outdoor coil can collect frost. In a reverse-cycle defrost sequence the unit temporarily redirects heat to that coil. Supply heat can dip even with demand and compressor still active. Trend heat request, defrost status, outdoor coil condition, auxiliary heat and delivered temperature through return to heating. The reversing-valve polarity, defrost termination and backup stages depend on the installed controls. A brief dip during a documented defrost and a persistent cooling response after defrost suggest different investigations.

Recognize a heat-pump terminal

A heat pump reverses the refrigerant circuit so the indoor coil can release heat or absorb it. On a water-source unit the loop is the other heat source or sink. A compressor proof point alone is compatible with either mode. Use the requested mode, manufacturer-specific reversing-valve sequence and the measured entering and leaving air temperatures to establish which direction heat actually moves.

Two simultaneous services in a DOAS building
  1. DOAS dries and delivers outdoor air
  2. Ventilation reaches the zone
  3. Zone terminal handles sensible load
  4. Zone temperature and dew point show separate outcomes

Normal operation

Example training conditions

  • At one occupied terminal the airflow target is 450 cfm and a hood reads 445 cfm total supply. A separate measured outdoor intake at the air handler serves multiple zones.
  • Terminal supply includes recirculated air. Ventilation verification requires the outdoor-air path and the applicable distribution calculation.

Worked service example

A bank of fan-coil offices feels humid while all thermostats are satisfied.

Recorded field evidence · training example

  • Zone 74°F with a 64°F dew point
  • DOAS supply dew point 63°F against a project target of 53°F
  • Outdoor-air branch flow matches design at the affected offices

The ventilation air is arriving with more moisture than intended. The common DOAS drying stage is the next measurement location. Replacing several terminal fans would leave that moisture load in place.

Field procedure

  1. Identify the equipment responsible for outside air and the equipment serving zone temperature.
  2. Compare actual terminal flow or fan and water response with its target.
  3. Compare zone and DOAS dew points with the design condition and document both air paths.

Hands-on exercise

Compare two air samples at the same dry-bulb temperature and different humidity. Locate the sample with the higher dew point.

Psychrometric chart and cooling-coil test

At standard atmospheric pressure, compare two samples at the same dry bulb and coil surface temperature. Record a dry coil, then raise relative humidity until the model predicts condensation. The chart shows 20–100% RH in 20-point steps.

Psychrometric chart. Entering air 75°F at 35% relative humidity. Humidity ratio 6.4 grams per kilogram of dry air.01020304045556575859520%40%60%80%100%Water vapor (g/kg dry air)Dry-bulb temperature (°F)

Circle · entering air. Square · leaving air when within chart limits. Coil model uses 1,000 cfm and up to 18,000 Btu/h of cooling.

Dew point 45.5°F · entering enthalpy 25.0 Btu/lb dry air · leaving 58.3°F · condensate 0.00 lb/h

Unit 6 service call

The heating valve is at 100%. Why is the discharge air still cold?

Trace load, air and heat from the unit to the occupied zone and verify automatic recovery. Bring back the source, reading and time of your strongest observation.

Open case simulator

Knowledge check

Pass at 80%.

1. A zone receives 500 cfm of supply air. Which additional evidence is needed before treating all 500 cfm as outdoor ventilation?
2. A hood measures 340 cfm at one terminal against a 400 cfm target. What percentage of target is being delivered?
3. Terminal airflow is on target and its primary inlet air is cool, yet discharge from the terminal is much warmer during a cooling complaint. Which local process is worth checking?
4. What observation establishes that a heat pump is delivering heat to its indoor airstream?
5. At 100% damper position a VAV box delivers only half its flow target. Which check is most discriminating?

Field takeaways

  • A zone can need moisture removal while its dry-bulb target is satisfied.
  • Trace central ventilation and local conditioning as separate services.

References and further reading